This letter serves to update you on the progress of our Land development Project. Elaine Ville Housing Development is pleased to announce that significant infrastructure work has begun at our site at Plantation Providence, East Bank Demerara.

Status report
  1. The fence for the Gated Community has begun.
  2. Concrete drains for Phase 1 & Phase 2 will be completed within 30 days.
  3. The water system in phase 1 and phase 2 will be operational in 60-90days
  4. The infrastructure for Electricity in phase 1 and phase 2 will be operational within 60-90 days
  5. All roads are now completed up to sub base
  6. Some Purchasers have commenced construction.
  7. Construction of the five model houses listed below has begun.
We still have available the following sizes of lands for Sale
Acres Sqft
0.124 5,401
0.25 10,890
0.50 21,780
0.55 23,958
2.0 87,120
3.0 130,680
4.058 176,766

Amenities will include a swimming pool, clubhouse and tennis court. For home financing contact Citizen Bank retail lending officer at +592-226-1705, ext 2206.